We received the following question from an Intervals customer.
I'm new to Intervals and was looking at the list of projects and noticed that some tasks are marked as unstarted. I've looked at one of the tasks and made a comment. Does that mark it as started?
A task will be included with unstarted tasks until time has been added to the task. Tasks that have not had any time tracked will be listed as unstarted. If you click on the number of unstarted tasks on the project listing you will be taken to the task listing page where the unstarted tasks are listed.
In addition to the project listing, the Project Landscape report shows unstarted tasks as well. If you want to review budgets, time data, and task data in one place the Project Landscape report is worth checking out.